The basement
of cottage #7 with the forms removed. June 29, 2005
|
 |
| |
 |
Workers move
toward the completion of the basement's interior walls. The pipes
coming out of the blocks are for the laundry room. (July 19, 2005)
|
| |
| |
|
Interior walls
in the basement of cottage #7 begin to take shape. (July 13, 2005) |
 |
| |
|
|
 |
The first
walls of cottage #4 go up as framing begins! (August 4, 2005)
|
| |
|
|
Constructing
walls on site was determined to be the most cost effective way to
build the cottages.
All the walls
are made of 2" x 6" material to increase the thickness
of the insulation, which is critical for having an energy efficient
building envelop. (August 4, 2005) |
 |
| |
|
|
 |
Roof
trusses have been delivered for cottages #3 and #4. They were
manufactured in a local truss making shop. (August 10, 2005)
|
| |
|
|
The first
story of cottage #4 takes shape as sheathing has been applied.
The oriented
strand board (OSB) selected for this project are made with a glue
that doesn't have harmful off gassing. (August 5, 2005) |
 |
| |
|
|
 |
Framing for
the second story of cottage #3 begins to take shape. (August 8,
2005)
|
The roof trusses
are being installed on cottage #3. The bedrooms will be on the left
- with two on first and two on second floor.
The central
area will contain the stairwell and the bathrooms.
The part on
the right will be the living room area with spacious window areas
and decks. (August 16, 2005) |
 |
| |
|
|
 |
There are
many angles to calculate!
(August 16,
2005)
|
| Workers place steel reinforcing rods in the foundation for the wind
turbine tower. The base is 16' x 16' x 4'. The tower will be 100'
tall. (August 4, 2005) |
 |
| |
|
|
 |
Construction workers
finish the top of the concrete poured for the wind turbine tower
base. Placing the anchor bolts accurately was a critical issue.
This concrete contains
fly ash (the same as all the other poured concrete), which is
another way of using recycled material. (August 4, 2005)
|
| |
|
|