Laying the Foundation May 20 - June 3

See our list of sustainable features

Site Preparation with Sustainability in Mind (photo series April 21 to May 16)

 

The mechanical subcontractors assemble the drains in the basement of cottage #7. (June 3, 2005)

Sustainable Feature: Waste water will be processed through a wetland cell and recirculating sand filter to purify it

 
 

Pea gravel is poured into the basement of cottage #7. The gravel will be leveled in preparation for pouring the concrete floor. (June 3, 2005)

Sustainable Feature: Construction traffic is kept close to the building site

 
   

Trencher digs the footers for cottages #3 and #4, which will be build on concrete slabs. (June 3, 2005)

     

Footers show the footprint of cottage #7. (June 1, 2005)

Sustainable Feature: Basement adds space without increasing the size of the building's "footprint" on the landscape

     

The first concrete is poured in to footer forms for cottage #7. (May
31, 2005)

Sustainable Feature: Construction traffic is kept close to the building site

     
 Footer forms and rebar for the foundation of cottage #7. (May 27, 2005)

 

     
Dr. LisaRenee English, Director of Environmental Studies, and Dr. Dale Hess, Professor of Agroecology envision teaching opportunities in what will be the basement of the initial classroom building. (May 25, 2005)
     

Excavation of the basement for the classroom/office building 5/20/05

Sustainable Feature: Wide track excavator used to limit compaction